Feed aggregator

Beneath the Pagoda Palace, foundations of San Francisco’s history

Featured News - Mon, 09/30/2013 - 12:15

john+fatherjohn

Father John Takahashi and Central Subway Program Director John Funghi stand beside concrete blocks that once formed the foundation of a historic North Beach church.

Earlier this month, construction crews demolishing the Pagoda Palace unearthed a long-lost piece of San Francisco history: the foundations of a church that stood on these grounds more than a century ago.

The Holy Trinity Orthodox Cathedral, now located at 1520 Green Street, once stood in North Beach at the corner of Powell Street and Columbus Avenue. Built in 1888, the dramatic onion-domed structure was completely destroyed by the great San Francisco earthquake and fire of 1906. All that remained were five bronze bells – and they survived because they were off site at the time, being repaired. The church relocated to the Green Street location soon after, opening in 1909.

Last week a concrete block from the old church’s foundations joined the bells at the Green Street cathedral. After construction crews unearthed the foundations, we contacted Father John Takahashi, the senior priest of the Holy Trinity Orthodox Cathedral, to inform him of our discovery. We also invited him to visit the construction site and see the newly uncovered relics of his church’s past.

holytrinitycathedral

The Holy Trinity Cathedral on Powell Street, circa 1890.

Once on site, Father John spoke with Central Subway Program Director John Funghi, and the Central Subway team gave Father John a block of concrete from the old foundations. The block will now live in the garden of the Green Street cathedral.

Central Subway crews discovered the historic foundations while dismantling the thick concrete slab that formed the base of the Pagoda Palace Theatre. Once the slab was removed, the outlines of the foundation revealed themselves amidst dirt and rubble.

Archeologists and construction personnel examined the unearthed foundations and concluded that they were consistent with building practices in the late 19th century. The absence of rebar, the consistency of the concrete and the size of the aggregate in it helped support this conclusion.

With a piece of the old church now safely preserved, crews then broke apart what remained of the foundations to make room for the next phase of Central Subway construction, and the next chapter in the life of this storied North Beach site.

Categories: News

Construction Update | Sept. 28-Oct. 7

Construction Updates - Fri, 09/27/2013 - 17:19

130925_1045_Pagoda

The Pagoda Palace site this week, after our crews completed demolishing the former theater.

During the next 10 days, tunneling and tunneling preparatory work will continue in southern SoMa, Union Square and North Beach. Work to prepare for station construction is continuing in Chinatown and northern SoMa.

For descriptions of construction impacts in each neighborhood, click here or on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by October 7:

  • Southern SoMa (Harrison to King/Berry): During the week of September 30, one lane of the I-80 off-ramp at 4th and Bryant may close. 4th Street between Harrison and Bryant may fully close some evenings and weekends to allow for the installation of tunnel boring machine segments. Two lanes of traffic will remain open at all other times. Contact us at central.subway@sfmta.com if you have questions about the closure schedule. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
  • Northern SoMa (Market to Harrison):  On 4th Street between Folsom and Harrison, the parking lane and one lane of traffic on the east side of the street will close Saturday, September 28 to allow for ground improvement work. 4th Street between Howard and Folsom will remain open to traffic, with demolition of the 76 gas station commencing next week. On 4th Street between Market and Stevenson, at least three lanes of traffic will be open.
  • Chinatown: Station contractor Tutor Perini will install monitoring devices and cap utilities at the Chinatown Station site (933-949 Stockton Street). Several parking spaces may be closed on the east side of Stockton Street and on both sides of Washington Street adjacent to the building. The sidewalk adjacent to the building will be closed to pedestrians for approximately two weeks. A partial lane closure may be in effect on Washington Street just west of Stockton Street. Night work will be underway from October 2-4, with traffic impacted at the intersection of Stockton and Washington on these nights.
  • North Beach: Construction of a retrieval shaft, to be used to remove two tunnel boring machines, is commencing at the Pagoda Palace site. The first activity is to install a sound wall that will buffer construction noise. Construction hours are Monday to Saturday, 7 a.m. to 7 p.m. All local roadways will remain open. Parking and walkways may be impacted in front of the Pagoda Palace property while equipment mobilization is in progress.

At these locations, current construction impacts are planned to continue until October 7:

  • Union Square: Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.

We appreciate your patience and support while we build this essential upgrade to San Francisco’s public transportation system.

Categories: Construction Updates

Construction Update Sept. 7- Sept.16

Construction Updates - Mon, 09/09/2013 - 11:45







Normal
0




false
false
false

EN-US
X-NONE
X-NONE

























DefSemiHidden="true" DefQFormat="false" DefPriority="99"
LatentStyleCount="267">
UnhideWhenUsed="false" QFormat="true" Name="Normal"/>
UnhideWhenUsed="false" QFormat="true" Name="heading 1"/>


















UnhideWhenUsed="false" QFormat="true" Name="Title"/>

UnhideWhenUsed="false" QFormat="true" Name="Subtitle"/>
UnhideWhenUsed="false" QFormat="true" Name="Strong"/>
UnhideWhenUsed="false" QFormat="true" Name="Emphasis"/>
UnhideWhenUsed="false" Name="Table Grid"/>

UnhideWhenUsed="false" QFormat="true" Name="No Spacing"/>
UnhideWhenUsed="false" Name="Light Shading"/>
UnhideWhenUsed="false" Name="Light List"/>
UnhideWhenUsed="false" Name="Light Grid"/>
UnhideWhenUsed="false" Name="Medium Shading 1"/>
UnhideWhenUsed="false" Name="Medium Shading 2"/>
UnhideWhenUsed="false" Name="Medium List 1"/>
UnhideWhenUsed="false" Name="Medium List 2"/>
UnhideWhenUsed="false" Name="Medium Grid 1"/>
UnhideWhenUsed="false" Name="Medium Grid 2"/>
UnhideWhenUsed="false" Name="Medium Grid 3"/>
UnhideWhenUsed="false" Name="Dark List"/>
UnhideWhenUsed="false" Name="Colorful Shading"/>
UnhideWhenUsed="false" Name="Colorful List"/>
UnhideWhenUsed="false" Name="Colorful Grid"/>
UnhideWhenUsed="false" Name="Light Shading Accent 1"/>
UnhideWhenUsed="false" Name="Light List Accent 1"/>
UnhideWhenUsed="false" Name="Light Grid Accent 1"/>
UnhideWhenUsed="false" Name="Medium Shading 1 Accent 1"/>
UnhideWhenUsed="false" Name="Medium Shading 2 Accent 1"/>
UnhideWhenUsed="false" Name="Medium List 1 Accent 1"/>

UnhideWhenUsed="false" QFormat="true" Name="List Paragraph"/>
UnhideWhenUsed="false" QFormat="true" Name="Quote"/>
UnhideWhenUsed="false" QFormat="true" Name="Intense Quote"/>
UnhideWhenUsed="false" Name="Medium List 2 Accent 1"/>
UnhideWhenUsed="false" Name="Medium Grid 1 Accent 1"/>
UnhideWhenUsed="false" Name="Medium Grid 2 Accent 1"/>
UnhideWhenUsed="false" Name="Medium Grid 3 Accent 1"/>
UnhideWhenUsed="false" Name="Dark List Accent 1"/>
UnhideWhenUsed="false" Name="Colorful Shading Accent 1"/>
UnhideWhenUsed="false" Name="Colorful List Accent 1"/>
UnhideWhenUsed="false" Name="Colorful Grid Accent 1"/>
UnhideWhenUsed="false" Name="Light Shading Accent 2"/>
UnhideWhenUsed="false" Name="Light List Accent 2"/>
UnhideWhenUsed="false" Name="Light Grid Accent 2"/>
UnhideWhenUsed="false" Name="Medium Shading 1 Accent 2"/>
UnhideWhenUsed="false" Name="Medium Shading 2 Accent 2"/>
UnhideWhenUsed="false" Name="Medium List 1 Accent 2"/>
UnhideWhenUsed="false" Name="Medium List 2 Accent 2"/>
UnhideWhenUsed="false" Name="Medium Grid 1 Accent 2"/>
UnhideWhenUsed="false" Name="Medium Grid 2 Accent 2"/>
UnhideWhenUsed="false" Name="Medium Grid 3 Accent 2"/>
UnhideWhenUsed="false" Name="Dark List Accent 2"/>
UnhideWhenUsed="false" Name="Colorful Shading Accent 2"/>
UnhideWhenUsed="false" Name="Colorful List Accent 2"/>
UnhideWhenUsed="false" Name="Colorful Grid Accent 2"/>
UnhideWhenUsed="false" Name="Light Shading Accent 3"/>
UnhideWhenUsed="false" Name="Light List Accent 3"/>
UnhideWhenUsed="false" Name="Light Grid Accent 3"/>
UnhideWhenUsed="false" Name="Medium Shading 1 Accent 3"/>
UnhideWhenUsed="false" Name="Medium Shading 2 Accent 3"/>
UnhideWhenUsed="false" Name="Medium List 1 Accent 3"/>
UnhideWhenUsed="false" Name="Medium List 2 Accent 3"/>
UnhideWhenUsed="false" Name="Medium Grid 1 Accent 3"/>
UnhideWhenUsed="false" Name="Medium Grid 2 Accent 3"/>
UnhideWhenUsed="false" Name="Medium Grid 3 Accent 3"/>
UnhideWhenUsed="false" Name="Dark List Accent 3"/>
UnhideWhenUsed="false" Name="Colorful Shading Accent 3"/>
UnhideWhenUsed="false" Name="Colorful List Accent 3"/>
UnhideWhenUsed="false" Name="Colorful Grid Accent 3"/>
UnhideWhenUsed="false" Name="Light Shading Accent 4"/>
UnhideWhenUsed="false" Name="Light List Accent 4"/>
UnhideWhenUsed="false" Name="Light Grid Accent 4"/>
UnhideWhenUsed="false" Name="Medium Shading 1 Accent 4"/>
UnhideWhenUsed="false" Name="Medium Shading 2 Accent 4"/>
UnhideWhenUsed="false" Name="Medium List 1 Accent 4"/>
UnhideWhenUsed="false" Name="Medium List 2 Accent 4"/>
UnhideWhenUsed="false" Name="Medium Grid 1 Accent 4"/>
UnhideWhenUsed="false" Name="Medium Grid 2 Accent 4"/>
UnhideWhenUsed="false" Name="Medium Grid 3 Accent 4"/>
UnhideWhenUsed="false" Name="Dark List Accent 4"/>
UnhideWhenUsed="false" Name="Colorful Shading Accent 4"/>
UnhideWhenUsed="false" Name="Colorful List Accent 4"/>
UnhideWhenUsed="false" Name="Colorful Grid Accent 4"/>
UnhideWhenUsed="false" Name="Light Shading Accent 5"/>
UnhideWhenUsed="false" Name="Light List Accent 5"/>
UnhideWhenUsed="false" Name="Light Grid Accent 5"/>
UnhideWhenUsed="false" Name="Medium Shading 1 Accent 5"/>
UnhideWhenUsed="false" Name="Medium Shading 2 Accent 5"/>
UnhideWhenUsed="false" Name="Medium List 1 Accent 5"/>
UnhideWhenUsed="false" Name="Medium List 2 Accent 5"/>
UnhideWhenUsed="false" Name="Medium Grid 1 Accent 5"/>
UnhideWhenUsed="false" Name="Medium Grid 2 Accent 5"/>
UnhideWhenUsed="false" Name="Medium Grid 3 Accent 5"/>
UnhideWhenUsed="false" Name="Dark List Accent 5"/>
UnhideWhenUsed="false" Name="Colorful Shading Accent 5"/>
UnhideWhenUsed="false" Name="Colorful List Accent 5"/>
UnhideWhenUsed="false" Name="Colorful Grid Accent 5"/>
UnhideWhenUsed="false" Name="Light Shading Accent 6"/>
UnhideWhenUsed="false" Name="Light List Accent 6"/>
UnhideWhenUsed="false" Name="Light Grid Accent 6"/>
UnhideWhenUsed="false" Name="Medium Shading 1 Accent 6"/>
UnhideWhenUsed="false" Name="Medium Shading 2 Accent 6"/>
UnhideWhenUsed="false" Name="Medium List 1 Accent 6"/>
UnhideWhenUsed="false" Name="Medium List 2 Accent 6"/>
UnhideWhenUsed="false" Name="Medium Grid 1 Accent 6"/>
UnhideWhenUsed="false" Name="Medium Grid 2 Accent 6"/>
UnhideWhenUsed="false" Name="Medium Grid 3 Accent 6"/>
UnhideWhenUsed="false" Name="Dark List Accent 6"/>
UnhideWhenUsed="false" Name="Colorful Shading Accent 6"/>
UnhideWhenUsed="false" Name="Colorful List Accent 6"/>
UnhideWhenUsed="false" Name="Colorful Grid Accent 6"/>
UnhideWhenUsed="false" QFormat="true" Name="Subtle Emphasis"/>
UnhideWhenUsed="false" QFormat="true" Name="Intense Emphasis"/>
UnhideWhenUsed="false" QFormat="true" Name="Subtle Reference"/>
UnhideWhenUsed="false" QFormat="true" Name="Intense Reference"/>
UnhideWhenUsed="false" QFormat="true" Name="Book Title"/>



/* Style Definitions */ table.MsoNormalTable {mso-style-name:"Table Normal"; mso-tstyle-rowband-size:0; mso-tstyle-colband-size:0; mso-style-noshow:yes; mso-style-priority:99; mso-style-parent:""; mso-padding-alt:0in 5.4pt 0in 5.4pt; mso-para-margin:0in; mso-para-margin-bottom:.0001pt; mso-pagination:widow-orphan; font-size:10.0pt; font-family:"Times New Roman","serif";}

Crews continue to prepare tunnel boring machine Big Alma for tunneling.

Crews continue to prepare tunnel boring machine Big Alma for tunneling.

Central Subway construction is starting this fall in Chinatown. Please join us on September 10 for a community meeting to learn more about upcoming work and ask any questions you may have. The meeting will be held at the Gum Moon Women’s Residence, 940 Washington Street, at 4 p.m.

During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, demolition of the Pagoda Palace will continue. Central Subway construction is planned to begin in Chinatown in mid-to-late September.

For descriptions of construction impacts in each neighborhood, scroll down or click on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by September 16:

  • Northern SoMa (Market to Harrison): On 4th Street between Howard and Folsom, the construction zone will move from the east side of the street to the west side starting early next week. Two lanes of traffic will remain open at all times. On 4th Street between Market and Stevenson, two traffic lanes will remain closed on the east side of the street.
  • Chinatown: No construction planned.
  • North Beach:  Work will be in progress within the Pagoda Palace this Saturday from 8 a.m. to 4 p.m. On Monday, September 9, from 1 a.m. to 5 a.m., the contractor will remove a specialized excavator from the site. Equipment demobilization will require a brief closure of Powell Street between Union and Columbus and Union Street between Columbus and Powell. During this time, parking will be impacted on both blocks. At all other times, both streets will remain open and parking will be impacted only in front of the Pagoda Palace property.

At these locations, current construction impacts are planned to continue until September 16:

  • Southern SoMa (Harrison to King/Berry): 4th Street between Harrison and Bryant may fully close some evenings and weekends to allow for the installation of tunnel boring machine segments. Two lanes of traffic will remain open at all other times. Contact us at central.subway@sfmta.com if you have questions about the closure schedule. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
  • Union Square: Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.

We appreciate your patience and support while we build this essential upgrade to San Francisco’s public transportation system.

Categories: Construction Updates

Construction Update Aug. 30-Sept. 9

Construction Updates - Mon, 09/09/2013 - 11:33
Construction continues in Union Square, where we are constructing underground walls on Stockton Street.

Construction continues in Union Square, where we are constructing underground walls on Stockton Street.

During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, demolition of the Pagoda Palace will continue. No Central Subway construction is planned in Chinatown.

In observance of the Labor Day Holiday, no Central Subway construction is planned for SoMa, Moscone, and Union Square/Market Street.

For descriptions of construction impacts in each neighborhood, scroll down or click on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by September 9:

  • Southern SoMa (Harrison to King/Berry): 4th Street between Harrison and Bryant may fully close some evenings and weekends starting Wednesday, September 4, to allow for installation of tunnel boring machine segments. Two lanes of traffic will remain open at all other times. Contact us at central.subway@sfmta.com if you have questions about the closure schedule. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
  • North Beach: Work will be in progress this Saturday from 7 a.m. to 3:30 p.m. demolishing the back brick wall by hand and off-haul materials from the site. Parking may be impacted in front of the Pagoda Palace property. The sidewalk in front of the property may be closed.

At these locations, current construction impacts are planned to continue until September 9:

  • Northern SoMa (Market to Harrison): Two lanes of traffic will remain closed on 4th Street between Howard and Folsom. On 4th Street between Market and Stevenson, two traffic lanes will remain closed on the eastern side of the street.
  • Union Square: Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.

We appreciate your patience and support while we build this essential upgrade to San Francisco’s public transportation system.

Categories: Construction Updates

Construction Update | Aug. 24-Sept. 2

Construction Updates - Fri, 08/23/2013 - 16:35

130820_1004_Pagoda

This week crews dismantled the facade of the Pagoda Palace, a former movie theater in North Beach that stood vacant for 20 years. Next year we will remove the tunnel boring machines from the ground at this location.

During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, demolition of the Pagoda Palace will continue. No Central Subway construction is planned in Chinatown.

For descriptions of construction impacts in each neighborhood, click here or on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by September 2:

  • Southern SoMa (Harrison to King/Berry): 4th Street between Harrison and Bryant may fully close some evenings and weekends starting Tuesday, August 27, to allow for installation of tunnel boring machine segments. Two lanes of traffic will remain open at all other times. Contact us at central.subway@sfmta.com if you have questions about the closure schedule. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
  • North Beach: The contractor has demolished enough of the Pagoda Palace to reopen Powell Street between Columbus and Union starting Saturday, August 24. The traffic lane still may be narrowed at times. The 39 Coit will return to its regular route. Work will be in progress this Saturday, August 24, from 7 a.m. to 12 noon to off-haul materials from the site. Parking will be impacted in front of the Pagoda Palace property. The sidewalk in front of the property may be closed.

At these locations, current construction impacts are planned to continue until September 2:

  • Northern SoMa (Market to Harrison): Two lanes of traffic will remain closed on 4th Street between Howard and Folsom. On 4th Street between Market and Stevenson, two traffic lanes will remain closed on the eastern side of the street.
  • Chinatown: No construction planned.
  • Union Square: Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.

We appreciate your patience and support while we build this essential upgrade to San Francisco’s public transportation system.

Categories: Construction Updates

Construction Update | August 17-26

Construction Updates - Fri, 08/16/2013 - 17:02

130815_1008_Ellis

On Ellis Street, crews are drilling tubes into the earth underground. When the tunnel boring machines pass below, we will inject grout through the tubes, improving the ground.

During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, demolition of the Pagoda Palace will continue. No Central Subway construction is planned in Chinatown.

For descriptions of construction impacts in each neighborhood, click here or on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by August 26:

  • North Beach: For approximately five days, starting Monday, August 19, through traffic on Powell Street between Columbus Avenue and Union Street will be restricted during working hours (7 a.m. to 3:30 p.m.). Local vehicle access to Powell Street will be provided from Union Street. At the end of each working day, the contractor will re-establish the regular traffic pattern. This temporary traffic modification will allow us to enhance public safety protections while demolishing the building’s facade. See this diagram for details. Parking will be impacted in front of the Pagoda Palace property. The sidewalk in front of the property may be closed.

At these locations, current construction impacts are planned to continue until August 26:

  • Southern SoMa (Harrison to King/Berry): Two lanes of traffic will remain open on 4th Street between Harrison and Bryant. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
  • Northern SoMa (Market to Harrison): Two lanes of traffic will remain closed on 4th Street between Howard and Folsom. On 4th Street between Market and Stevenson, the sidewalk and two traffic lanes will remain closed on the eastern side of the street.
  • Chinatown: No construction planned.
  • Union Square: Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.

We appreciate your patience and support while we build this essential upgrade to San Francisco’s public transportation system.

Categories: Construction Updates

Construction Update | August 10-19

Construction Updates - Fri, 08/09/2013 - 20:00

Taken from a nearby roof, this photo shows our construction site at 4th and Folsom and the gas station that will be demolished to make way for the future Yerba Buena/Moscone Station.

During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, demolition of the Pagoda Palace will continue. No Central Subway construction is planned in Chinatown.

For descriptions of construction impacts in each neighborhood, click here or on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by August 19:

  • Union Square: Water line work will be underway on O’Farrell Street between Stockton and Powell from Monday to Friday next week. To facilitate this work, O’Farrell Street may be narrowed to one lane from 9 a.m. to 3 p.m. on weekdays.Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.

At these locations, current construction impacts are planned to continue until
August 19:

  • Southern SoMa (Harrison to King/Berry): Two lanes of traffic will remain open on 4th Street between Harrison and Bryant. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
  • Northern SoMa (Market to Harrison): Two lanes of traffic will remain closed on 4th Street between Howard and Folsom. On 4th Street between Market and Stevenson, the sidewalk and two traffic lanes will remain closed on the eastern side of the street.
  • Chinatown: No construction planned.
  • North Beach: Demolition of the Pagoda Palace is continuing in North Beach. Parking will be impacted in front of the Pagoda Palace property. The sidewalk in front of the property may be closed. Powell Street between Union and Columbus will remain open to traffic, but the traffic lane may be narrowed. For more information about demolition, check out this fact sheet and the North Beach section of this email.

We appreciate your patience and support while we build this essential upgrade to San Francisco’s public transportation system.

Categories: Construction Updates

Construction Update | August 3-12

Construction Updates - Fri, 08/02/2013 - 16:56

130731_1179_launchbox

This week we hosted members of the American Public Transportation Association on a tour of project sites, including the tunnel launch box. Here, Central Subway Deputy Program Manager Albert Hoe shows tunnel boring machine Big Alma to tour goers.

During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, demolition of the Pagoda Palace will continue. No Central Subway construction is planned in Chinatown.

For descriptions of construction impacts in each neighborhood, click here or on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by August 12:

  • Union Square: Next week, both lanes of O’Farrell Street between Stockton and Powell will remain open to vehicle traffic, with no water line work underway. Water line work is planned to recommence the week of August 12. Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.
  • North Beach: Demolition of the Pagoda Palace is continuing in North Beach. On Monday, August 5, from 1 a.m. to 5 a.m., the contractor will move a specialized excavator onto the site to commence demolition of the building facade. Equipment mobilization will require a brief closure of Powell Street between Union and Columbus and Union Street between Columbus and Powell. During this time, parking will be impacted on both blocks. At all other times, both streets will remain open and parking will be impacted only in front of the Pagoda Palace property. For more information about demolition, check out this fact sheet and the North Beach section of this email.

At these locations, current construction impacts are planned to continue until
August 12:

  • Southern SoMa (Harrison to King/Berry): No full closures of 4th Street between Harrison and Bryant are planned for this period. Two lanes of traffic will remain open at all other times. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
  • Northern SoMa (Market to Harrison): Two lanes of traffic will remain closed on 4th Street between Howard and Folsom. On 4th Street between Market and Stevenson, the sidewalk and two traffic lanes will remain closed on the eastern side of the street.
  • Chinatown: No construction planned.

We appreciate your patience and support while we build this essential upgrade to San Francisco’s public transportation system.

Categories: Construction Updates

Tunneling crews assemble Big Alma, the Central Subway’s second TBM

Featured News - Thu, 08/01/2013 - 17:21

130718_1199_bigalmacutterhead

Late in the night last month, crews installed the cutter head of tunnel boring machine (TBM) Big Alma. The massive machine’s cylindrical shield was already in place below.

Big Alma has arrived. The massive tunneling machine — the identical twin of recently launched Mom Chung — is now under assembly underground. Last month, tunneling crews lowered large sections of Big Alma into the tunnel launch box, the major excavation under 4th Street between Harrison and Bryant where tunneling begins. After about two months of assembly, Big Alma will begin building a tunnel parallel to Mom Chung’s, extending the Muni Metro T Third Line through SoMa, Union Square and Chinatown.

The photos in this post show the installation of Big Alma’s cutter head. The cutter head, a spinning excavator at the front of the machine, will dig through bedrock, clay and sand as Big Alma travels north beneath 4th Street, Stockton Street and Columbus Avenue. This major component of the TBM is about 20 feet in diameter and weighs about 143,000 pounds. While tunneling is underway, the cutter head will pump out an environmentally safe, soap-like foam to condition the ground as it cuts through the earth like a cheese grater. Once loosened, spoils pass through holes in the cutter head for transport out of the tunnel.

To learn more about the TBMs and their tunneling journey, follow them on Twitter. They’re @BigAlmatheTBM and @MomChungtheTBM.

130718_1129_bigalmacutterhead

A large red crane, called a gantry crane, lifts the cutter head from the ground.

130718_1135_bigalmacutterhead

When Big Alma tunnels, these wheels will spin to loosen the ground, aided by an environmentally safe, soap-like foam that conditions it.

130718_1161_bigalmacutterhead

Operated by our tunneling crews, the crane lifts the cutter head into a vertical position to allow for installation.

130718_1179_bigalmacutterhead

Crews help stabilize the cutter head before lowering it underground.

130718_1194_bigalmacutterhead

The crane moves the cutter head into position over the tunnel launch box, where Big Alma’s cylindrical shield awaits.

130718_1198_bigalmacutterhead

The shield, already underground, will stabilize the tunnel and form a watertight barrier while mining is in progress. Concrete tunnel segments are installed within the back of the shield and bolted together by tunneling crews.

130718_1206_bigalmacutterhead

Above the shield, the cutter head descends into the excavation.

130718_1213_bigalmacutterhead

The front of the shield, before the cutter head is installed. During tunneling, excavated ground spoils will pass through the hole at the bottom for transport out of the tunnel.

130718_1216_bigalmacutterhead

The cutter head continues its descent into the excavation.

130718_1227_bigalmacutterhead

Once the cutter head is lowered, crews work to connect it to the shield.

 

130718_1249_bigalmacutterhead

To connect the TBM segments, crews bolt them together. Later, they will reinforce the connections with welding.

130718_1317_bigalmacutterhead

The TBM assembly team poses in front of Big Alma. We thank our dedicated crews for all their hard work.

 

Categories: News

TBM Mom Chung launches, beginning tunnel construction beneath SF

Construction Updates - Fri, 07/26/2013 - 17:11


This video shows some of the first ground spoils excavated after our first TBM, Mom Chung, launched this week.

This week tunnel boring machine (TBM) Mom Chung started digging, kicking off construction of San Francisco’s first new subway tunnel in decades.  Over the next 10 months, the 350-foot-long, 750-ton machine will excavate and construct the tunnel that southbound T Third Line trains will use when the Central Subway opens in 2019.

As Mom Chung travels, you can follow her on Twitter — she’s @MomChungtheTBM. Her twin sister, Big Alma, recently arrived in San Francisco. After about six weeks of assembly underground, she will begin constructing a tunnel parallel to Mom Chung’s. (You can follow Big Alma at @BigAlmatheTBM.)

The tunnels are a key component in extending the Muni Metro T Third Line through SoMa, Union Square and Chinatown, vastly improving transit in these neighborhoods.

The Tunneling Journey

Mom Chung and Big Alma will excavate and construct the 1.5-mile-long tunnels at a pace of approximately 40 feet per day, though their pace will vary based on ground conditions and other factors. Most of their journey will be through two major ground formations: the Franciscan complex, a bedrock formation that forms Nob Hill; and the Colma formation, a dense mixture of sand and clay.

The TBMs will be so far beneath the surface – between 40 and 120 feet underground – that no vibration or noise will be felt above ground when they pass below.


In this video, a welder works on the TBM’s trailing gear.

How TBMs Work

The machines consist of three main sections: a rotating cutter wheel (the cutter head), a cylindrical steel shell (the shield) and a 300-foot train of tunnel-building mechanisms (the trailing gear).

130723_1205_launchbox

This conveyor belt on top of Mom Chung’s trailing gear will help transport ground spoils out of the tunnel. In the background you can see the cutter head of our second TBM, Big Alma.

The cutter head, a spinning excavator at the front of the machine, pumps out an environmentally safe, soap-like foam to condition the ground as it cuts through the earth like a cheese grater. Once loosened, spoils pass through holes in the cutter head and onto a large screw. The screw carries the spoils onto a series of conveyors for transport out of the tunnel.

To launch, Mom Chung pushed off of a steel frame as her cutter head began to spin.

130724_1000_launchbox

The large concrete segments shown here are what will form the Central Subway tunnels. The TBMs will install them, and crews will bolt them together, as the machines move forward.

As she tunnels, Mom Chung will stop every five feet to install the concrete segments that make up the tunnel’s lining. The concrete segments are installed within the back of the TBM’s cylindrical shield. The machine lifts the segments into place, and then crews bolt them together. Hydraulic jacks within the shield then push off of the newly installed tunnel lining, propelling the massive machine forward.

These concrete rings, already installed, are held in place by hydraulic arms (seen on the left) as the machine moves forward.

A crew of about 10 people operates the machine and bolts the tunnel segments together. Crews will be at work 24 hours a day, six days a week to build the Central Subway’s tunnels.

Learn More

Want to find out more about the Central Subway’s complex, high-tech tunneling machines? Check out the following documents:

Categories: Construction Updates

TBM Mom Chung launches, beginning tunnel construction beneath SF

Featured News - Fri, 07/26/2013 - 17:11


This video shows some of the first ground spoils excavated after our first TBM, Mom Chung, launched this week.

This week tunnel boring machine (TBM) Mom Chung started digging, kicking off construction of San Francisco’s first new subway tunnel in decades.  Over the next 10 months, the 350-foot-long, 750-ton machine will excavate and construct the tunnel that southbound T Third Line trains will use when the Central Subway opens in 2019.

As Mom Chung travels, you can follow her on Twitter — she’s @MomChungtheTBM. Her twin sister, Big Alma, recently arrived in San Francisco. After about six weeks of assembly underground, she will begin constructing a tunnel parallel to Mom Chung’s. (You can follow Big Alma at @BigAlmatheTBM.)

The tunnels are a key component in extending the Muni Metro T Third Line through SoMa, Union Square and Chinatown, vastly improving transit in these neighborhoods.

The Tunneling Journey

Mom Chung and Big Alma will excavate and construct the 1.5-mile-long tunnels at a pace of approximately 40 feet per day, though their pace will vary based on ground conditions and other factors. Most of their journey will be through two major ground formations: the Franciscan complex, a bedrock formation that forms Nob Hill; and the Colma formation, a dense mixture of sand and clay.

The TBMs will be so far beneath the surface – between 40 and 120 feet underground – that no vibration or noise will be felt above ground when they pass below.


In this video, a welder works on the TBM’s trailing gear.

How TBMs Work

The machines consist of three main sections: a rotating cutter wheel (the cutter head), a cylindrical steel shell (the shield) and a 300-foot train of tunnel-building mechanisms (the trailing gear).

130723_1205_launchbox

This conveyor belt on top of Mom Chung’s trailing gear will help transport ground spoils out of the tunnel. In the background you can see the cutter head of our second TBM, Big Alma.

The cutter head, a spinning excavator at the front of the machine, pumps out an environmentally safe, soap-like foam to condition the ground as it cuts through the earth like a cheese grater. Once loosened, spoils pass through holes in the cutter head and onto a large screw. The screw carries the spoils onto a series of conveyors for transport out of the tunnel.

To launch, Mom Chung pushed off of a steel frame as her cutter head began to spin.

130724_1000_launchbox

The large concrete segments shown here are what will form the Central Subway tunnels. The TBMs will install them, and crews will bolt them together, as the machines move forward.

As she tunnels, Mom Chung will stop every five feet to install the concrete segments that make up the tunnel’s lining. The concrete segments are installed within the back of the TBM’s cylindrical shield. The machine lifts the segments into place, and then crews bolt them together. Hydraulic jacks within the shield then push off of the newly installed tunnel lining, propelling the massive machine forward.

These concrete rings, already installed, are held in place by hydraulic arms (seen on the left) as the machine moves forward.

A crew of about 10 people operates the machine and bolts the tunnel segments together. Crews will be at work 24 hours a day, six days a week to build the Central Subway’s tunnels.

Learn More

Want to find out more about the Central Subway’s complex, high-tech tunneling machines? Check out the following documents:

Categories: News

Construction Update | July 13-22

Construction Updates - Fri, 07/12/2013 - 16:32

130709_1069_ums

People pass by our Stockton Street construction site on a sunny day earlier this week.

During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, demolition of the Pagoda Palace is planned to begin. No Central Subway construction is planned in Chinatown.

For descriptions of construction impacts in each neighborhood, click here or on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by July 22:

  • Southern SoMa (Harrison to King/Berry): Full closure of 4th Street between Harrison and Bryant will continue some evenings and weekends, including all day Saturday, July 13. Two lanes of traffic will remain open at all other times. Contact us at central.subway@sfmta.com if you have questions about the closure schedule. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
  • North Beach: Demolition of the Pagoda Palace Theater is scheduled to take approximately four weeks to complete. For more information about construction at this site, check out this fact sheet.

At these locations, current construction impacts are planned to continue until July 22:

  • Northern SoMa (Market to Harrison): Two lanes of traffic will remain closed on 4th Street between Howard and Folsom. On 4th Street between Market and Stevenson, the sidewalk and two traffic lanes will remain closed on the eastern side of the street.
  • Union Square: Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.
  • Chinatown: No construction planned

We appreciate your patience and support while we build this essential upgrade to San Francisco’s public transportation system.

Categories: Construction Updates

Construction Details | Pagoda Palace Demolition

Featured News - Thu, 07/11/2013 - 12:20

pagoda

The Central Subway tunnel will end at this site in North Beach, now home to the old Pagoda Palace Theater.

Since last summer, the SFMTA has worked closely with the North Beach community and multiple city agencies to relocate the retrieval site of the Central Subway’s tunnel boring machines (TBMs) from its original site on Columbus Avenue. After a series of community meetings and based on feedback from the community, the TBMs will now be retrieved at 1731-1741 Powell Street, known as the Pagoda Palace.

The first phase of construction at this site is the demolition of the Pagoda Palace. We expect this activity to take approximately four weeks to complete, including mobilization and site clean-up.

The building will be demolished using specialized equipment called a nibbler and crusher. This equipment is like a scissor that cuts the building into small pieces of rubble. Working from the sidewalk and parking lane in front of the Pagoda Palace, the contractor will take down the facade of the building, starting with the tallest point. Once there is enough clearance, the contractor will move inside the property line and complete the demolition from within.

After demolishing the building, we will construct a retrieval shaft within the property lines at 1731-1741 Powell Street. The retrieval shaft is an excavation of about 45 ft. by 49 ft., with a depth of approximately 42 ft. We will provide additional details about retrieval shaft construction before it begins.

The SFMTA is working closely with local contractor MH Construction to minimize construction impacts as much as possible while demolition is underway. For more information, check out this fact sheet. Construction details are below.

Planned construction (all dates approximate):

  • Disconnect utilities within building (week of July 8)
  • Set up pedestrian detour (week of July 15)
  • Mobilize demolition equipment (week of July 15)
  • Demolish building (approx. July 15-26)
  • Remove demolished building pieces (week of July 29)
  • Grade the site (week of July 29)
  • Construction hours will be Monday to Friday, 7 a.m. to 3:30 p.m.
  • Demolition takes approximately two weeks to complete, with two additional weeks required to prepare the site, remove the building pieces and grade the lot.

Traffic, transit and pedestrian impacts:

  • Area of impact: Powell Street and Columbus Avenue between Filbert and Union streets
  • The sidewalk in front of 1731-1741 Powell Street will be impacted
  • The Muni 39 Coit may be temporarily rerouted, but no stops will be impacted (see fact sheet for details)
  • Parking restrictions will be in effect in front of the Pagoda Palace on Powell Street and Columbus Avenue
  • Powell Street between Union and Columbus will remain open to traffic, but the traffic lane may be narrowed
  • The contractor will maintain access to adjacent businesses and facilitate the flow of traffic during work hours
  • Dust will be monitored and controlled, and noise will be kept within required decibel levels (see fact sheet for details)

We will provide additional updates via email and on our blog as work proceeds. Should you have any questions, please contact North Beach liaison Andrea Baker at 415.351.8427.

Thank you for your patience and support.

Categories: News

Construction Details | Pagoda Palace Demolition

Construction Updates - Thu, 07/11/2013 - 12:20

pagoda

The Central Subway tunnel will end at this site in North Beach, now home to the old Pagoda Palace Theater.

Since last summer, the SFMTA has worked closely with the North Beach community and multiple city agencies to relocate the retrieval site of the Central Subway’s tunnel boring machines (TBMs) from its original site on Columbus Avenue. After a series of community meetings and based on feedback from the community, the TBMs will now be retrieved at 1731-1741 Powell Street, known as the Pagoda Palace.

The first phase of construction at this site is the demolition of the Pagoda Palace. We expect this activity to take approximately four weeks to complete, including mobilization and site clean-up.

The building will be demolished using specialized equipment called a nibbler and crusher. This equipment is like a scissor that cuts the building into small pieces of rubble. Working from the sidewalk and parking lane in front of the Pagoda Palace, the contractor will take down the facade of the building, starting with the tallest point. Once there is enough clearance, the contractor will move inside the property line and complete the demolition from within.

After demolishing the building, we will construct a retrieval shaft within the property lines at 1731-1741 Powell Street. The retrieval shaft is an excavation of about 45 ft. by 49 ft., with a depth of approximately 42 ft. We will provide additional details about retrieval shaft construction before it begins.

The SFMTA is working closely with local contractor MH Construction to minimize construction impacts as much as possible while demolition is underway. For more information, check out this fact sheet. Construction details are below.

Planned construction (all dates approximate):

  • Disconnect utilities within building (week of July 8)
  • Set up pedestrian detour (week of July 15)
  • Mobilize demolition equipment (week of July 15)
  • Demolish building (approx. July 15-26)
  • Remove demolished building pieces (week of July 29)
  • Grade the site (week of July 29)
  • Construction hours will be Monday to Friday, 7 a.m. to 3:30 p.m.
  • Demolition takes approximately two weeks to complete, with two additional weeks required to prepare the site, remove the building pieces and grade the lot.

Traffic, transit and pedestrian impacts:

  • Area of impact: Powell Street and Columbus Avenue between Filbert and Union streets
  • The sidewalk in front of 1731-1741 Powell Street will be impacted
  • The Muni 39 Coit may be temporarily rerouted, but no stops will be impacted (see fact sheet for details)
  • Parking restrictions will be in effect in front of the Pagoda Palace on Powell Street and Columbus Avenue
  • Powell Street between Union and Columbus will remain open to traffic, but the traffic lane may be narrowed
  • The contractor will maintain access to adjacent businesses and facilitate the flow of traffic during work hours
  • Dust will be monitored and controlled, and noise will be kept within required decibel levels (see fact sheet for details)

We will provide additional updates via email and on our blog as work proceeds. Should you have any questions, please contact North Beach liaison Andrea Baker at 415.351.8427.

Thank you for your patience and support.

Categories: Construction Updates

Construction Update | June 29-July 15

Construction Updates - Fri, 06/28/2013 - 16:32

130625_1000_ybm

On Stockton Street, we are using this machine to construct underground walls. The walls will be incorporated into the Union Square/Market Street Station.

Note: Because of  the July 4 holiday, this construction update covers construction impacts through July 15. We will not send a construction update email next Friday, July 5; however, we will provide additional details about construction in North Beach early next week. Please contact us at central.subway@sfmta.com with any questions.

During the next 17 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, Pagoda Palace demolition contractor MH Construction will perform surveys of the site. No Central Subway construction is planned in Chinatown.

In honor of the holiday, Central Subway construction will pause on Thursday, July 4.

For descriptions of construction impacts in each neighborhood, click here or on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by July 15:

  • North Beach: Demolition of the Pagoda Palace Theater is scheduled to start Monday, July 8. For more information about construction at this site, check out this construction notice. We will provide detailed information about construction impacts next week, before demolition begins.
  • Northern SoMa (Market to Harrison): To allow for ground improvements, construction will be underway for 24 hours a day from June 28 until the morning of June 30 on 4th Street between Howard and Folsom (details in the Northern SoMa section). Two lanes of traffic will remain closed on 4th Street between Howard and Folsom. On 4th Street between Market and Stevenson, the sidewalk and two traffic lanes will remain closed on the eastern side of the street.

At these locations, current construction impacts are planned to continue until July 15:

  • Southern SoMa (Harrison to King/Berry): Full closure of 4th Street between Harrison and Bryant will continue some evenings and weekends. Two lanes of traffic will remain open at all other times. Contact us at central.subway@sfmta.com if you have questions about the closure schedule. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
  • Union Square: Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.
  • Chinatown: No construction planned

We appreciate your patience and support while we build this essential upgrade to San Francisco’s public transportation system.

Categories: Construction Updates

Construction Update | June 22-July 1

Construction Updates - Fri, 06/21/2013 - 17:30

130619_1109_launchboxba09f7

Crews are continuing to assemble tunnel boring machine Mom Chung. The black roll of ribbon is her conveyor belt, where spoils will be transported out of the tunnel.

During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, Pagoda Palace demolition contractor MH Construction will perform surveys of the site. No Central Subway construction is planned in Chinatown.

For descriptions of construction impacts in each neighborhood, click here or on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by July 1:

  • Northern SoMa (Market to Harrison):  Two lanes of traffic will remain closed on 4th Street between Howard and Folsom, but the traffic configuration will change (details in the Northern SoMa section). Construction will be underway on Saturdays until further notice. On 4th Street between Market and Stevenson, the sidewalk and two traffic lanes will remain closed on the eastern side of the street.
  • North Beach: Pagoda Palace demolition contractor MH Construction will perform surveys of 1731-1741 Powell Street. For more information about construction at this site, check out this construction notice. We will provide detailed information about construction impacts before demolition begins.

At these locations, current construction impacts are planned to continue until July 1:

  • Southern SoMa (Harrison to King/Berry): Full closure of 4th Street between Harrison and Bryant will continue some evenings and weekends. Two lanes of traffic will remain open at all other times. Contact us at central.subway@sfmta.com if you have questions about the closure schedule. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
  • Union Square: Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.
  • Chinatown: No construction planned

We appreciate your patience and support while we build this essential upgrade to San Francisco’s public transportation system.

Categories: Construction Updates

Construction Update | June 15-24

Construction Updates - Fri, 06/14/2013 - 17:13

130613_1046_ellis

About 80 feet below Ellis Street, we’re installing pipes into the ground around this shaft. We’ll use the pipes to inject grout into the ground, improving soil conditions near the existing Muni and BART tunnels.

During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned in Chinatown or North Beach.

For descriptions of construction impacts in each neighborhood, click here or on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by June 24:

  • Northern SoMa (Market to Harrison):  Two lanes of traffic will remain closed on 4th Street between Howard and Folsom, but the traffic configuration will change (details in the Northern SoMa section). Construction will be underway on Saturdays until further notice. On 4th Street between Market and Stevenson, the sidewalk and two traffic lanes will remain closed on the eastern side of the street.

At these locations, current construction impacts are planned to continue until June 24:

  • Southern SoMa (Harrison to King/Berry): Full closure of 4th Street between Harrison and Bryant will continue some evenings and weekends. Two lanes of traffic will remain open at all other times. Contact us at central.subway@sfmta.comif you have questions about the closure schedule. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
  • Union Square: Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.
  • Chinatown: No construction planned
  • North Beach: No construction planned before June 24, but demolition of the Pagoda Palace is scheduled to begin in June. For more information, check out thisconstruction notice.

We appreciate your patience and support while we build this essential upgrade to San Francisco’s public transportation system.

Categories: Construction Updates

Construction Update | June 8-17

Construction Updates - Fri, 06/07/2013 - 15:43

130604_1018_launchbox

Crews continue to prepare tunnel boring machine Mom Chung for launch.

During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned in Chinatown or North Beach.

For descriptions of construction impacts in each neighborhood, click here or on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by June 17:

  • Northern SoMa (Market to Harrison):  Two lanes of traffic will remain closed on 4th Street between Howard and Folsom, but the traffic configuration may change (details in the Northern SoMa section). Construction will be underway this Saturday, June 8, and next Saturday, June 15, on this block. On 4th Street between Market and Stevenson, the sidewalk and two traffic lanes will remain closed on the eastern side of the street.

At these locations, current construction impacts are planned to continue until June 17:

  • Southern SoMa (Harrison to King/Berry): Full closure of 4th Street between Harrison and Bryant will continue some evenings and weekends. Two lanes of traffic will remain open at all other times. Contact us at central.subway@sfmta.com if you have questions about the closure schedule. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
  • Union Square: Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.
  • Chinatown: No construction planned
  • North Beach: No construction planned before June 17, but demolition of the Pagoda Palace is scheduled to begin in June. For more information, check out this construction notice.

We appreciate your patience and support while we build this essential upgrade to San Francisco’s public transportation system.

Categories: Construction Updates

Photos: Mayor Lee, public officials, community members celebrate TBM Mom Chung and upcoming start of tunneling

Featured News - Thu, 06/06/2013 - 16:05

130530_1253_tbm_vip_event

A tour group visits tunnel boring machine Mom Chung beneath busy 4th Street.

Tunnel boring machine Mom Chung is almost assembled and just about ready for launch. This month, the 350-foot-long, 750-ton tunnel-building behemoth will begin her journey north beneath the streets of San Francisco, constructing the city’s first new subway tunnel in decades.

Last week we celebrated Mom Chung’s upcoming journey with an event at the site where tunneling will begin. After speeches by Mayor Edwin M. Lee, Democratic Leader Nancy Pelosi’s Chief of Staff Robert Edmonson, Board of Supervisors President David Chiu, District 6 Supervisor Jane Kim and others, guests toured the underground site where Mom Chung is being assembled. They sent her off by signing their names on her cylindrical shield, wishing her a safe and successful voyage beneath SoMa, Union Square, Chinatown and North Beach.

The photos below are of the event, held last Thursday on and below 4th Street. For more photos, visit us on Flickr. To find out more about the event, check out this press release from the SFMTA.

130530_1000_tbm_vip_event

Before the event, the stage was set with safety gear for special guests and honored speakers.

130530_1018_tbm_vip_event

Reporters set up cameras, preparing for the arrival of Mayor Lee and other special guests.

130530_1062_tbm_vip_event

A cheerful Mayor Lee talks about the many benefits of the Central Subway — reducing travel times, connecting San Francisco’s neighborhoods and preparing for the growth expected in the city in coming years and decades.

130530_1034_tbm_vip_event

Supervisors Jane Kim and David Chiu listen to Mayor Lee’s speech. The Central Subway (and Mom Chung) will travel through their districts.

130530_1159_tbm_vip_event

Mayor Lee prepares to cut the cake decorated with TBM Mom Chung. Thanks to Victoria Pastry for creating this delicious treat.

130530_1188_tbm_vip_event

Central Subway Program Director John Funghi leads the first tour of the excavation, known as a launch box, where Mom Chung is being assembled and will begin tunneling.

130530_1195_tbm_vip_event

At the entrance to the launch box, tour goers look with awe upon Mom Chung.

 

130530_1233_tbm_vip_event

Mayor Lee signs Mom Chung. The TBM will help build “our future San Francisco.”

130530_1238_tbm_vip_event

Others, including Supervisor Chiu, sign their names and messages on the TBM.

  130530_1256_tbm_vip_event

Gina Low Weiss, grandniece of Dr. Margaret “Mom” Chung, after whom the TBM is named, signs her name and writes her message on the machine.

130530_1283_tbm_vip_event

This section of Mom Chung, known as the trailing gear, performs a variety of functions, including carrying excavated spoils out of the tunnel and bringing concrete tunnel segments in.

130530_1285_tbm_vip_event

After the tour, participants exited the launch box, returning outside to a warm, sunny day.

 

Categories: News

Photos: Mayor Lee, public officials, community members celebrate TBM Mom Chung and upcoming start of tunneling

Press Releases - Thu, 06/06/2013 - 16:05

130530_1253_tbm_vip_event

A tour group visits tunnel boring machine Mom Chung beneath busy 4th Street.

Tunnel boring machine Mom Chung is almost assembled and just about ready for launch. This month, the 350-foot-long, 750-ton tunnel-building behemoth will begin her journey north beneath the streets of San Francisco, constructing the city’s first new subway tunnel in decades.

Last week we celebrated Mom Chung’s upcoming journey with an event at the site where tunneling will begin. After speeches by Mayor Edwin M. Lee, Democratic Leader Nancy Pelosi’s Chief of Staff Robert Edmonson, Board of Supervisors President David Chiu, District 6 Supervisor Jane Kim and others, guests toured the underground site where Mom Chung is being assembled. They sent her off by signing their names on her cylindrical shield, wishing her a safe and successful voyage beneath SoMa, Union Square, Chinatown and North Beach.

The photos below are of the event, held last Thursday on and below 4th Street. For more photos, visit us on Flickr. To find out more about the event, check out this press release from the SFMTA.

130530_1000_tbm_vip_event

Before the event, the stage was set with safety gear for special guests and honored speakers.

130530_1018_tbm_vip_event

Reporters set up cameras, preparing for the arrival of Mayor Lee and other special guests.

130530_1062_tbm_vip_event

A cheerful Mayor Lee talks about the many benefits of the Central Subway — reducing travel times, connecting San Francisco’s neighborhoods and preparing for the growth expected in the city in coming years and decades.

130530_1034_tbm_vip_event

Supervisors Jane Kim and David Chiu listen to Mayor Lee’s speech. The Central Subway (and Mom Chung) will travel through their districts.

130530_1159_tbm_vip_event

Mayor Lee prepares to cut the cake decorated with TBM Mom Chung. Thanks to Victoria Pastry for creating this delicious treat.

130530_1188_tbm_vip_event

Central Subway Program Director John Funghi leads the first tour of the excavation, known as a launch box, where Mom Chung is being assembled and will begin tunneling.

130530_1195_tbm_vip_event

At the entrance to the launch box, tour goers look with awe upon Mom Chung.

 

130530_1233_tbm_vip_event

Mayor Lee signs Mom Chung. The TBM will help build “our future San Francisco.”

130530_1238_tbm_vip_event

Others, including Supervisor Chiu, sign their names and messages on the TBM.

  130530_1256_tbm_vip_event

Gina Low Weiss, grandniece of Dr. Margaret “Mom” Chung, after whom the TBM is named, signs her name and writes her message on the machine.

130530_1283_tbm_vip_event

This section of Mom Chung, known as the trailing gear, performs a variety of functions, including carrying excavated spoils out of the tunnel and bringing concrete tunnel segments in.

130530_1285_tbm_vip_event

After the tour, participants exited the launch box, returning outside to a warm, sunny day.

 

Categories: Press Releases

Pages

Theme by Danetsoft and Danang Probo Sayekti inspired by Maksimer